  • Question

  • Is there any task equivalent to the SingleNode property for a job?

    msdn.microsoft.com/en-us/library/microsoft.hpc.scheduler.ischedulerjob.singlenode(v=vs.85).aspx

    Or can I somehow ensure that a multi-core task runs on the same compute node (while the job is split on multiple nodes)?

    I obtain it now by setting e.g. two cores per subscribed sockets and request a socket but then I can only use one task size without taking nodes offline and change the number of subscribed sockets.

    Thursday, June 18, 2015 9:13 AM

Answers

  • In our current implementation, your solution might be the best way to do the work. You can also try put your task in one job if you don't have many tasks to accomplish this.

    Qiufang Shi

    • Marked as answer by Thomas Kofoed Tuesday, August 25, 2015 12:14 PM
    Tuesday, June 30, 2015 4:09 PM