Mark completed a task in Project server 2010 RRS feed

  • Question

  • How a user mark a task completed in Project Server 2010? if for example the planning time was 8 hours but the user completed the task in 5 hours?

    tks

    Juan Alvarado


    Juan Alvarado - MVP SQL SERVER
    Monday, August 9, 2010 2:47 PM

Answers

  • Hello Juan,

    Under My Tasks, open the task and set remaining hours to 0.

    Cheers!

    MIchael Wharton, MBA, PMP, MCT


    Sincerely, Michael Wharton, MBA, PMP, MCT, MCSD, MCSE+I, MCDBA www.WhartonComputer.com
    Monday, August 9, 2010 3:26 PM