locked
Timesheets forbidden in the future? RRS feed

  • Question

  • Hi,

    I'm trying a lot of scenarios about timesheets in PWA 2010. As my resources are overallocated now, I created a new project 3 weeks in the future. I published several times the project with its assignments. In Server Settings > Timesheets Settings and default I checked "Allow future time reporting". But no assignment appears in the resource timesheet (excepted 1 out of 8).

    What could be the cause of that? 

    Tuesday, March 1, 2011 3:33 PM

Answers

  • Hi,

    "Allow future time reporting" dooes allow reporting, but it does not display all assignments in each timesheet. It is allowed to enter hours, but resource has to add them into his/her timesheet by Insert Row - Insert Task. It will open a dialog "add existing task".

    Does that help?
    Barbara

    • Marked as answer by WLID1966 Tuesday, March 1, 2011 6:34 PM
    Tuesday, March 1, 2011 6:29 PM

All replies

  • Hi,

    "Allow future time reporting" dooes allow reporting, but it does not display all assignments in each timesheet. It is allowed to enter hours, but resource has to add them into his/her timesheet by Insert Row - Insert Task. It will open a dialog "add existing task".

    Does that help?
    Barbara

    • Marked as answer by WLID1966 Tuesday, March 1, 2011 6:34 PM
    Tuesday, March 1, 2011 6:29 PM
  • That helps!

    Thanks Barbara

    Tuesday, March 1, 2011 6:34 PM