Project scope status RRS feed

  • Question

  • Hi All,

    We want to display the scope status in project center as graphical indicator based on "if there is any new tasks added after the schedule is baselined, the total duration of all new tasks need to be compared with the project duration i.e. scope status= (sum of new tasks duration/project duration)*100 ". How can we achieve this?


    Thanks in advance, Arun

    Tuesday, April 1, 2014 2:55 AM

Answers

  • Hi Arun,

    You could create a task custom field equal to the duration if there is no baseline finish date and roll it up at summary row with a sum.

    Then you could create a project custom field equal to this calculated duration divided by the project duration.

    Hope this helps.


    Guillaume Rouyre - MBA, MCP, MCTS

    • Marked as answer by arun_2014 Tuesday, April 8, 2014 3:47 PM
    Tuesday, April 1, 2014 8:24 AM