locked
excel cubes RRS feed

  • Question

  • hy, why in the excel cube to analyze some project i have to put the field in the value settings average? why if I put sum the result that show do no is the same that appear in the project.

    Friday, November 19, 2010 7:16 PM

Answers

  • Let me see if I understand your question. The project value is different in the cube than in the actual project? If this is the case it can have a view different reasons.

    - hvae you rebuild the cube? the cubes need to be rebuild before the latest update becomes available

    - the information you maintain in the project is published? you will need to publish the project and after the cube is rebuild you should see the same values in both the cube and the project.

    Let me know if this is your issue or if it is something else
    Thanks


    Marc Soester [MVP] http://marcsoester.blogspot.com
    Friday, November 19, 2010 10:51 PM