Project in PWA 2010 does not reflect changes made in Project Pro 2010 RRS feed

  • Question

  • A project created in PWA using manual scheduled mode for a set of tasks.  Saved, closed & checked in via PWA.  Opened in Project Pro 2010 and modified all tasks from manual to auto.  Saved and checked in.  Viewing project via PWA doesn't reflect changes made unless I choose "edit" on the project.  Even once closing / checking back in - it reverts to showing manual mode for all tasks in PWA.  Open in Project Pro 2010 and it shows them correctly as Auto.  Any ideas?


    Tyler McLaughlin
    Thursday, May 27, 2010 3:55 PM

Answers

  • Did you publish the schedule?
     
     
    - Andrew Lavinsky
    Blog: http://blogs.catapultsystems.com/epm
     
     
     
    • Marked as answer by Sriram E Friday, May 28, 2010 12:52 AM
    Thursday, May 27, 2010 4:26 PM
  • Schedule published and things updated correctly.  Thank you -
    Tyler McLaughlin
    • Marked as answer by Sriram E Friday, May 28, 2010 12:53 AM
    Thursday, May 27, 2010 5:16 PM

All replies

  • Did you publish the schedule?
     
     
    - Andrew Lavinsky
    Blog: http://blogs.catapultsystems.com/epm
     
     
     
    • Marked as answer by Sriram E Friday, May 28, 2010 12:52 AM
    Thursday, May 27, 2010 4:26 PM
  • Schedule published and things updated correctly.  Thank you -
    Tyler McLaughlin
    • Marked as answer by Sriram E Friday, May 28, 2010 12:53 AM
    Thursday, May 27, 2010 5:16 PM