locked
Editing Projects via PWA RRS feed

  • Question

  • When I open a project for editing in PWA, I can edit data when I pick a "TASK" project view, but cant edit anything if i pick one of the ASSIGNMENT Project views. 

    Is this the way it should work or did i miss something?

    Wednesday, November 30, 2011 6:32 PM

Answers

  • BayouB --

    You are correct that Project Server 2010 limits you to editing only Tasks views in PWA.  You cannot edit either Assignment views or Resource views from the Project Center.  That is why the system displays a Task ribbon, along with a Project ribbon and an Options ribbon, when you open a project for editing in PWA.  This is one more limitation of many limitations with attempting to use the PWA interface to edit projects.  Hope this helps.


    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Wednesday, November 30, 2011 7:05 PM

All replies

  • BayouB --

    You are correct that Project Server 2010 limits you to editing only Tasks views in PWA.  You cannot edit either Assignment views or Resource views from the Project Center.  That is why the system displays a Task ribbon, along with a Project ribbon and an Options ribbon, when you open a project for editing in PWA.  This is one more limitation of many limitations with attempting to use the PWA interface to edit projects.  Hope this helps.


    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

    Wednesday, November 30, 2011 7:05 PM
  • Thanks!!
    Tuesday, December 6, 2011 8:15 PM