locked
AX2012 - Why can't Expiry Date be edited on Rebate Agreement? RRS feed

  • Question

  • Following Technet web page lists which fields can be edited: 

    Update a rebate agreement [AX 2012]

    I can edit all of the fields listed, apart from Start Date and Expiry Date.

    There are no transactions associated with the Rebate Agreement.

    What do I need to do to make the dates editable?

    Friday, August 2, 2013 8:15 AM

Answers

  • Figured it out.
    It was the ValidTimeStateUpdate property on form data source.
    Changing it from CreateNewTimePeriod to Correction.
    Friday, August 2, 2013 11:27 AM