PWA 2010 Auto Schedule Changes the Manually Set Start Date
hi, Auto scheduling itself means it will set date date according to relationship between the task.Answered | 2 Replies | 8901 Views | Created by Curtis R - Saturday, June 11, 2011 12:26 AM | Last reply by Nur Nahar Mondal - Saturday, June 11, 2011 8:11 AM -
0 Votes
Server 2010 - Start Date on new Projects created in PWA
Setting the Start date of the project is one of about half a dozen initiating steps that the PM must do to properly initiate any new project, either in ...Answered | 2 Replies | 1956 Views | Created by Scott_CF - Wednesday, November 27, 2013 6:09 PM | Last reply by Dale Howard [MVP] - Wednesday, November 27, 2013 8:16 PM -
0 Votes
Unable to update tasks in PWA 2010
If you scroll down the page, you can find the "Task Mode Settings".. where you can make "Auto Schedule" the default for all 'New tasks'...Answered | 5 Replies | 8118 Views | Created by Venu Madduri - Tuesday, June 7, 2011 1:03 PM | Last reply by Venu Madduri - Tuesday, June 7, 2011 4:09 PM -
5 Votes
Unable to Change Project Start Date in Project Server 2013
Hi Vrij007, is your template scheduling from the FINISH date, rather than the start?Answered | 11 Replies | 5917 Views | Created by Vrij007 - Wednesday, February 18, 2015 4:07 PM | Last reply by Ben Howard [MVP] - Friday, June 19, 2015 11:07 AM -
0 Votes
Disable the ability to edit Start and Finish dates on the PWA
Hi Mark, Please review the VIEWS within PWA Settings and either set the fields to read only, or remove them from the view.Answered | 9 Replies | 11506 Views | Created by B.D - Monday, November 15, 2010 10:58 PM | Last reply by Ben Howard [MVP] - Wednesday, June 7, 2017 2:32 PM -
1 Votes
How to add Column in Schedule PDP (PWA 2010)
Then go to Server Settings / Manage Views and search your view in the Project section.Answered | 1 Replies | 2244 Views | Created by WLID1966 - Wednesday, June 18, 2014 7:27 AM | Last reply by Gérard Ducouret - Wednesday, June 18, 2014 7:52 AM -
2 Votes
Creation date of a Risk in PWA 2010
Thanks Dale, I inserted the two columns: Creation Date and Modification Date, but these fields are empty by default.Answered | 4 Replies | 4303 Views | Created by WLID1966 - Friday, October 26, 2012 1:07 PM | Last reply by Dale Howard [MVP] - Saturday, October 27, 2012 2:55 PM -
2 Votes
Deliverables in PWA 2010
"Sync Dependencies", on the other hand, CHANGES the SELECTED dependent tasks in the CONSUMING project to "sync" with the dates in the ...Answered | 4 Replies | 10396 Views | Created by WLID1966 - Thursday, October 6, 2011 7:41 AM | Last reply by Jackson Cole - Tuesday, September 3, 2013 12:16 PM -
0 Votes
How to modify Schedule PDP in PWA?
Server Settings > Manage views.Answered | 2 Replies | 7194 Views | Created by Asif Allauddin, PMP - Monday, September 19, 2011 11:07 AM | Last reply by PWMather - Monday, September 19, 2011 11:24 AM -
0 Votes
How to change color of current date line in PWA 2007?
And as i replied the same to my first reply to you that this is not possible in PWA 2010 and PWA 2007 as well.Answered | 7 Replies | 8699 Views | Created by Harmony K - Monday, August 8, 2011 8:30 AM | Last reply by Dale Howard [MVP] - Wednesday, August 10, 2011 12:30 PM -
0 Votes
Start date changed
Sounds like he hasn't set predecessor and successor relationships.Answered | 1 Replies | 9806 Views | Created by FrankDouvry - Friday, March 18, 2011 5:40 PM | Last reply by Andrew Lavinsky - Friday, March 18, 2011 8:35 PM -
0 Votes
PWA Error Project out of Date
In my case, I have got just 2 PDPs associated with EPT. one is for custom fields, and the other is for schedule.Answered | 5 Replies | 11502 Views | Created by cseaman1210 - Wednesday, November 3, 2010 8:50 PM | Last reply by Khurram Jamshed - Wednesday, March 27, 2013 9:27 AM -
1 Votes
PWA 2010 and Project Pro Template
Hi, The only option to use templates in projects created through PWA is to use a schedule template associated with an EPT.Answered | 1 Replies | 9458 Views | Created by WLID1966 - Saturday, December 4, 2010 9:55 PM | Last reply by Alexander.Burton - Saturday, December 4, 2010 11:00 PM -
0 Votes
Daily Schedule back up in PWA site,,how does it work??
(http://social.technet.microsoft.com/Forums/projectserver/en-US/d4463b5b-ba9b-455c-9903-462b7b809b95/daily-schedule-back-up-in-pwa-sitehow-does-it-work) ...Answered | 1 Replies | 2199 Views | Created by anuj astro - Friday, September 20, 2013 8:42 AM | Last reply by Barbara Henhapl - Friday, September 20, 2013 9:04 AM -
0 Votes
Scheduling problems in MS PROJECT 2010
Vijay -- When you specify the calendar values in an existing project, you need to manually change the time in the Start Date field in the Project ...Answered | 4 Replies | 2006 Views | Created by kumar ksv - Wednesday, April 2, 2014 10:44 AM | Last reply by Dale Howard [MVP] - Wednesday, April 2, 2014 2:31 PM -
0 Votes
How can I view the status date of a project plan in pwa?
In 2010 Microsoft Introduce project Editing and other features for schedule management in PWA .Answered | 10 Replies | 7913 Views | Created by Tian-Song Tsai - Friday, May 3, 2013 10:18 AM | Last reply by Tian-Song Tsai - Wednesday, May 15, 2013 1:26 AM -
0 Votes
PWA broken (shows exception) while restoring PWA site collection on another PWA in PS 2010
i DON'T need to restore the Project Server things (The projects, timesheets date, projects sitest etc), what i just want is the PWA site contents like branding, ...Answered | 3 Replies | 9120 Views | Created by Maaz Ibrahim - Sunday, April 10, 2011 5:06 PM | Last reply by Maaz Ibrahim - Sunday, April 10, 2011 8:28 PM -
0 Votes
When does the actual start date in appointments change
Hi Gary, The actual start is default to the create date unless you specify a different value on the form.Answered | 2 Replies | 2898 Views | Created by GaryMk - Tuesday, June 25, 2013 6:17 PM | Last reply by GaryMk - Wednesday, June 26, 2013 3:20 PM -
0 Votes
Setting start and finish date for project programatically in project server 2010
Actually from the initial project creation itself we need the correct dates to be reflected at the project level, so we have programatically created a summary task along ...Answered | 3 Replies | 10730 Views | Created by Rose 25 - Tuesday, March 8, 2011 12:28 PM | Last reply by Barbara Henhapl - Friday, March 11, 2011 5:56 AM -
0 Votes
Project 2010 - Auto Update Task Start (if not yet started)
I'll explore both options further otherwise the manual adjusting will be my backup, Kind regards MarkAnswered | 2 Replies | 2911 Views | Created by MarkS_LE - Monday, July 8, 2013 7:45 PM | Last reply by MarkS_LE - Wednesday, July 10, 2013 5:46 PM - Items 1 to 20 of 212971 Next ›