0 Votes
Setting default parameters for Resource Plans
I was afraid that was the case about the parameters.Answered | 2 Replies | 5899 Views | Created by Oscarin0557 - Tuesday, June 5, 2012 2:58 PM | Last reply by Oscarin0557 - Wednesday, June 6, 2012 6:18 PM -
0 Votes
2010 - Resource Plan Settings
Is it possible to set the default setup options for resource plans (i.e., time units, work format, etc..) in 2010?Answered | 2 Replies | 10822 Views | Created by Joe Blow 1234 - Tuesday, September 14, 2010 2:04 AM | Last reply by Joe Blow 1234 - Wednesday, September 15, 2010 9:52 PM -
0 Votes
Project Server Resource Plan
Currently you have this set to "Project Plan" so the Resource plan assignment data will be ignored.Answered | 5 Replies | 1927 Views | Created by arun_2014 - Monday, December 7, 2015 3:06 PM | Last reply by PWMather - Tuesday, December 8, 2015 1:46 PM -
0 Votes
Resource Planning
The general concept with resource planning, is that it is a high level view of what resources are need for a proposal.Answered | 4 Replies | 9600 Views | Created by slstein20 - Friday, November 12, 2010 9:00 PM | Last reply by Michael Wharton - Wednesday, November 17, 2010 8:55 PM -
0 Votes
Time Allocation on Resource Plans
Dave, Resource Plans are a 'planning' feature. they do not 'validate' the information you put in.Answered | 1 Replies | 6063 Views | Created by TheRealDaveK - Thursday, October 20, 2011 3:46 PM | Last reply by Prasanna Adavi - Thursday, October 20, 2011 6:38 PM -
0 Votes
Resource Planning Stage
Do you mean a complete project plan in project professional, with comitted resources in it?Answered | 8 Replies | 12681 Views | Created by Nairoukh - Monday, December 28, 2009 1:43 PM | Last reply by Jose Manuel Araya - Wednesday, July 18, 2012 2:23 AM -
0 Votes
Resource Plan doesn't get publish
We did do all that and the resource plan was working fine.Answered | 11 Replies | 13061 Views | Created by Hammad Mian - Monday, June 13, 2011 9:41 PM | Last reply by Dale Howard [MVP] - Wednesday, November 7, 2012 5:31 PM -
1 Votes
Resources Planning
One important requirement is to assign an activity (or a task) to an available resource.Answered | 2 Replies | 10103 Views | Created by Daniel_358 - Friday, July 30, 2010 10:57 AM | Last reply by Daniel_358 - Friday, July 30, 2010 2:19 PM -
0 Votes
Use of Proposed Booking feature for Resource Planning
That being said, I am going to dust off my memory of 2003, and see if I can walk you through resource planning process: 1) Map each of your ...Answered | 1 Replies | 9602 Views | Created by B N Bose - Sunday, February 13, 2011 10:03 PM | Last reply by Andrew Lavinsky - Monday, February 14, 2011 3:30 AM -
0 Votes
Set project plan to open in read-only as default setting
If on the contrary what you want is to have selected as default read-only even for the owners of the project, it is probably, as Michael says, with a macro, and this is ...Answered | 4 Replies | 10877 Views | Created by Dave Shultz - Wednesday, September 29, 2010 8:41 PM | Last reply by Gary Chefetz, MCITP, MCT, MVP - Wednesday, October 13, 2010 3:11 PM -
0 Votes
default settings in Resource Plans
2) Resource plans publish with their respective projects.Answered | 1 Replies | 6286 Views | Created by Oscarin0557 - Thursday, May 31, 2012 9:41 PM | Last reply by Gary Chefetz, MCITP, MCT, MVP - Tuesday, June 26, 2012 9:51 AM -
0 Votes
Resource plan performance issue 6000+ queries
The problem is that I need to update resource plan data so I need to use PSI because as you said, developing against the Published database is not supported by MS.Answered | 2 Replies | 6464 Views | Created by Clément Comte - Monday, August 8, 2011 10:03 AM | Last reply by Clément Comte - Tuesday, August 9, 2011 9:52 AM -
0 Votes
IMPORTANT: Usage of a percentage of Resource time on planning
The easiest way to do this would be to set the Max Units for each resource at 20% within the resource pool.Answered | 3 Replies | 10030 Views | Created by Konstantinos Christodoulakis - Thursday, March 3, 2011 8:36 PM | Last reply by Gary Chefetz, MCITP, MCT, MVP - Wednesday, March 9, 2011 3:40 PM -
0 Votes
set default text in fields
Aye thats a good point, your current settings there would prompt the script to run whenever the Mark Up field is changed which may not be what you are aiming for in the default ...Answered | 21 Replies | 5847 Views | Created by tcal0005 - Friday, July 8, 2011 8:34 AM | Last reply by tcal0005 - Tuesday, July 12, 2011 7:27 AM -
0 Votes
Portfolio Analysis with Time-phased Resource Planning
To answer your question why / What is the purpose of Time phased Resource Planning, here is an excerpt from Technet : Once you have created analyses and ...Answered | 2 Replies | 9897 Views | Created by John Doe Cal - Wednesday, March 16, 2011 2:58 AM | Last reply by Andrew Lavinsky - Wednesday, March 16, 2011 11:12 AM -
3 Votes
Enterprise Resources being dropped in the project plan
In the case of the plan that lost multiple resources/assignments, they have four separate users that edit the plan (I know, not best practice and risk in ...Answered | 10 Replies | 9120 Views | Created by OCBluejay - Friday, August 12, 2011 2:58 PM | Last reply by OCBluejay - Wednesday, August 17, 2011 4:15 PM -
1 Votes
Setting Field Defaults
I need to set the UOM for Opportunities and Quotes.Answered | 8 Replies | 6906 Views | Created by Greg Staples - Sunday, April 19, 2009 3:46 AM | Last reply by Melissa Ragsdale - Tuesday, October 18, 2011 3:31 PM -
0 Votes
Sample Proposal Workflow - Moving past "Resource Planning" stage?
Your portfolio analysis needs to also include a Resource Constraint Analysis.Answered | 3 Replies | 13772 Views | Created by Glenn Scott - Thursday, February 25, 2010 7:39 AM | Last reply by Marius Bunescu - Thursday, February 25, 2010 10:23 PM -
0 Votes
Timesheet Page Default Settings
Is there a way to administratively set the view, filter, and group-by settings so that all resources have a consistent default view in Project Server 2010?Answered | 2 Replies | 1808 Views | Created by Tom_Herrington - Wednesday, February 12, 2014 7:28 PM | Last reply by Tom_Herrington - Wednesday, February 12, 2014 9:39 PM -
0 Votes
Project Server 2010 SQL Report on Resource PLan Data
Hi, We have a PS 2010 setup, and our organization is planning to use PS 2010 Resource Plan feature for Resource Management for calculating demand ...Answered | 2 Replies | 3052 Views | Created by YLee_1980 - Monday, October 7, 2013 2:37 PM | Last reply by YLee_1980 - Wednesday, October 23, 2013 4:03 AM - Items 1 to 20 of 147684 Next ›