0 Votes
Time Allocation on Resource Plans
Dave, Resource Plans are a 'planning' feature. they do not 'validate' the information you put in.Answered | 1 Replies | 6042 Views | Created by TheRealDaveK - Thursday, October 20, 2011 3:46 PM | Last reply by Prasanna Adavi - Thursday, October 20, 2011 6:38 PM -
0 Votes
Resource Allocations
When connected to Project Server, Pro will show resource allocations for each project schedule that is currently open.Answered | 4 Replies | 8008 Views | Created by s_samira_21 - Tuesday, August 2, 2011 7:17 AM | Last reply by Project Admin1234 - Monday, June 16, 2014 4:45 PM -
0 Votes
Resource Management - Controlling allocation by calendar?
Lets not forget, the user determins when and for how long a resource is allocated to a task.Answered | 2 Replies | 7994 Views | Created by Thirteententh - Friday, November 26, 2010 4:07 PM | Last reply by Thirteententh - Monday, November 29, 2010 11:27 AM -
0 Votes
Resource Planning
The general concept with resource planning, is that it is a high level view of what resources are need for a proposal.Answered | 4 Replies | 9588 Views | Created by slstein20 - Friday, November 12, 2010 9:00 PM | Last reply by Michael Wharton - Wednesday, November 17, 2010 8:55 PM -
0 Votes
Portfolio Analysis with Time-phased Resource Planning
To answer your question why / What is the purpose of Time phased Resource Planning, here is an excerpt from Technet : Once you have created analyses and ...Answered | 2 Replies | 9889 Views | Created by John Doe Cal - Wednesday, March 16, 2011 2:58 AM | Last reply by Andrew Lavinsky - Wednesday, March 16, 2011 11:12 AM -
0 Votes
IMPORTANT: Usage of a percentage of Resource time on planning
Konstantinos: You can contour assignments for resources using either the Resource Usage View or the Task Usage view in Project.Answered | 3 Replies | 10017 Views | Created by Konstantinos Christodoulakis - Thursday, March 3, 2011 8:36 PM | Last reply by Gary Chefetz, MCITP, MCT, MVP - Wednesday, March 9, 2011 3:40 PM -
0 Votes
how to plan or allocate hours for sick time and other benefits?
Most people do not plan "sick time.Answered | 2 Replies | 2775 Views | Created by Green Legion 44 - Friday, June 7, 2013 6:42 PM | Last reply by Gary Chefetz, MCITP, MCT, MVP - Friday, June 7, 2013 9:21 PM -
0 Votes
How to keep allocation details of resources in each project?
Everytime I update this details in Project Plan and check In project in Project Server.Answered | 8 Replies | 9279 Views | Created by Rose 25 - Sunday, November 28, 2010 4:40 PM | Last reply by Dale Howard [MVP] - Thursday, July 5, 2012 3:32 PM -
0 Votes
A report that shows both resource capacity and project allocation
The only annoying thing about it is that every time you update the chart, the capacity (I have the data series set to a line graph against bars) line turns back into a bar and you have ...Answered | 10 Replies | 9630 Views | Created by ElliJ - Saturday, February 25, 2012 1:47 AM | Last reply by Ganesh P - Thursday, August 10, 2017 2:56 PM -
0 Votes
Project Server Resource Plan
Change the "Calculate From" option then Save and Publish the resource plan.Answered | 5 Replies | 1888 Views | Created by arun_2014 - Monday, December 7, 2015 3:06 PM | Last reply by PWMather - Tuesday, December 8, 2015 1:46 PM -
0 Votes
Resource Plan doesn't get publish
We did do all that and the resource plan was working fine.Answered | 11 Replies | 13047 Views | Created by Hammad Mian - Monday, June 13, 2011 9:41 PM | Last reply by Dale Howard [MVP] - Wednesday, November 7, 2012 5:31 PM -
0 Votes
Project Server 2010 - Resource Allocation set limits in an enterprise environment
Is there any way to restrict PM's from overallocating resources?Answered | 1 Replies | 6279 Views | Created by Donna Naomi - Friday, December 9, 2011 4:25 AM | Last reply by Dale Howard [MVP] - Friday, December 9, 2011 7:38 PM -
0 Votes
2010 - Resource Plan Settings
Is it possible to set the default setup options for resource plans (i.e., time units, work format, etc..) in 2010?Answered | 2 Replies | 10809 Views | Created by Joe Blow 1234 - Tuesday, September 14, 2010 2:04 AM | Last reply by Joe Blow 1234 - Wednesday, September 15, 2010 9:52 PM -
0 Votes
Resource Planning Stage
Do you mean a complete project plan in project professional, with comitted resources in it?Answered | 8 Replies | 12670 Views | Created by Nairoukh - Monday, December 28, 2009 1:43 PM | Last reply by Jose Manuel Araya - Wednesday, July 18, 2012 2:23 AM -
0 Votes
Use of Proposed Booking feature for Resource Planning
That being said, I am going to dust off my memory of 2003, and see if I can walk you through resource planning process: 1) Map each of your ...Answered | 1 Replies | 9592 Views | Created by B N Bose - Sunday, February 13, 2011 10:03 PM | Last reply by Andrew Lavinsky - Monday, February 14, 2011 3:30 AM -
0 Votes
Setting default parameters for Resource Plans
There is not a way to set the defaults for resource plans.Answered | 2 Replies | 5879 Views | Created by Oscarin0557 - Tuesday, June 5, 2012 2:58 PM | Last reply by Oscarin0557 - Wednesday, June 6, 2012 6:18 PM -
1 Votes
Resources Planning
One important requirement is to assign an activity (or a task) to an available resource.Answered | 2 Replies | 10095 Views | Created by Daniel_358 - Friday, July 30, 2010 10:57 AM | Last reply by Daniel_358 - Friday, July 30, 2010 2:19 PM -
0 Votes
Resource plan performance issue 6000+ queries
More the number of resources (in the resource plan) is important, more the loading time is long.Answered | 2 Replies | 6455 Views | Created by Clément Comte - Monday, August 8, 2011 10:03 AM | Last reply by Clément Comte - Tuesday, August 9, 2011 9:52 AM -
3 Votes
Enterprise Resources being dropped in the project plan
In the case of the plan that lost multiple resources/assignments, they have four separate users that edit the plan (I know, not best practice and risk in ...Answered | 10 Replies | 9109 Views | Created by OCBluejay - Friday, August 12, 2011 2:58 PM | Last reply by OCBluejay - Wednesday, August 17, 2011 4:15 PM -
0 Votes
Resource shows as overallocated but is not
I also believe that there are serious bugs in the resource usage views and the computation of resources overallocation flags, loading resources ...Answered | 12 Replies | 20702 Views | Created by smokief - Tuesday, January 24, 2012 9:07 PM | Last reply by pfinl - Tuesday, October 30, 2018 3:39 PM - Items 1 to 20 of 138587 Next ›