  • Hi,

    I have setup daily auto publish of projects using powershell and it works fine. However, the auto publish does not seems to be able to trigger the calculation services to compute the graphical indicator of my calculated custom field (with today information). Is there any way I could trigger the calculation services before publishing the project? I also found out that by saving the calculated custom field prior to the auto-publish action, it will trigger the calculation services. Alternatively, is there any powershell script that I could perform saving of enterprise custom field?

    Regards,
    Woon Woon, Gan

    03 Februari 2016 9:01

Semua Balasan

  • just change any project field back and forth and call Update() commando

    this will trigger the engine 

    $tempName=$Project.Name 
                $draftProject.Name = $projectName 
                $draftProject.Update()