"Move end of completed parts..." Java/PSI script

    Pertanyaan

  • Hi all.

    In my script I update "% complete" from Lotus to MS Project shedules on MSP Server.
    In MS Project App, in "enterprise global template" this setting (move end of ... and other) is switch on.

    But tasks updates without "move end of..." after script is complete.
    I don't use resources, all task have "Fixed unit tasks".

    I want, when I updated "% complete" on task with "Finish date" in Past, this task move on Status Date with correctly set "% complete" - see example.


    What was a problem? Where I wrong?
    This setting set in enterprise global template, calculation running on server...
    Kamis, 06 September 2018 07.26